News

Project Progress: Powerlink Roof Restoration

19
April

Woollam Constructions is making significant progress at Powerlink’s Virginia site. Roofing of stage 2A has commenced and will see 40% of roof area complete for handover to Powerlink by the end of April.

Structure is at 60% completion, with atrium structure erected and awaiting Danpalon sheeting. The team are currently completing external truss strengthening on the back area of the courtyard using a combination of elevated work platforms and scaffolding to remove and replace major structural members.

The relentless efforts of the site team to maintain quality and protect existing services have ensured exposure to rework is mitigated. We commend the project team’s efforts in overcoming initial setbacks in order streamline programming on such a challenging project.